Introduction

In 2009, the Albanian government privatised the national electrical energy distribution company, but retained 24 per cent of the company’s shares. ČEZ, the Czech company that bought the remaining 76 per cent, was considered to be a strategic investor by the Albanian government. After privatisation, the company was renamed ČEZ Shperndarje.

Country
Albania
Sector
Energy and natural resources
Offence
Abuse of power
Phase
Prelim. investigation

Description of the case

In 2009, the Albanian government privatised the national electrical energy distribution company, but retained 24 per cent of the company’s shares. ČEZ, the Czech company that bought the remaining 76 per cent, was considered to be a strategic investor by the Albanian government. After privatisation, the company was renamed ČEZ Shperndarje.

Owing to mismanagement by ČEZ, the company incurred heavy financial losses whilst its investments in the distribution network were considered insufficient by the Energy Regulatory Authority, which decided to revoke ČEZ's licences to operate in January 2013. Subsequent to the Albanian authority’s revocation of ČEZ’s licences, the Czech company sued the Albanian government under UNCITRAL arbitration rules on 15 May 2013 (see here and here).

The government decided by a Decision of the Council of Ministers No. 969, dated 25 October 2013, to appoint a working group for the purpose of settling the dispute with ČEZ. The settlement agreement was signed by both parties on 23 June 2014 and ratified by the Albanian Assembly on 31 July 2014 (see here and here).

The Albanian Supreme State Audit Institution (SSAI) conducted an audit of the procedures followed by the Albanian negotiating team in the settlement, and it alleged that the team had failed to keep records of the negotiations and to safeguard the taxpayer's interest when it agreed to pay a settlement that was not justified by ČEZ's financial records. According to the SSAI, the then Minister for Infrastructure and Energy Damian Gjiknuri had failed to safeguard the interest of the Albanian taxpayers by accepting the costs presented by ČEZ as fact without scrutinising the loan agreements that the company in Albania had made with ČEZ in Prague and with Albanian banks (see here).

In addition to Minister Gjiknuri’s failure as chief negotiator to capitalise on the company’s managerial and financial failures and strengthen the negotiating position of the Albanian government, he had involved only six of the 14 negotiators mandated in the prime minister’s order to establish the negotiating team. On 14 October 2015, the SSAI filed charges with the Prosecutor General’s Office against Minister Gjiknuri (as chief negotiator) and the state advocate general (as a member of the negotiating team) alleging that the state had incurred financial damages of €479 million because of their actions or inactions.

The Prosecutor General's Office decided to close the investigation of the case in June 2016 arguing that the facts confirmed by the investigation did not amount to a crime under Articles 248 and 25 of the Albanian Penal Code (abuse of power in collaboration). The SSAI appealed the prosecution's decision to the High Court, which decided in favour of the prosecution.

Every effort has been made to verify the accuracy of the information contained in this database. All information is believed to be correct as of December 2020. Nevertheless, Transparency International cannot accept responsibility for the consequences of its use for other purposes or in other contexts.